CLWA to Consider Cost Increases(January 9, 2006, as appeared in The Signal (Santa Clarita Valley)) The Castaic Lake Water Agency board of directors is set to consider on Wednesday two cost increases for services being performed by contractors working on the expansion of the agency’s administration building in Saugus. They are two “change orders,” one for the contract with Chino-based Moore Flooring, Inc., for an increase of $7,652, and the other with Laguna Hills-based Orange Builders, Inc. for an increase of $20,999 to “the fire suppression contract” as noted in the staff report. “During the past five months of construction, a number of items have arisen during construction including unknown or unforeseen buried utilities or conditions and/or clarification of contract documents that have resulted in additional costs,” the staff report said. They are two change orders out of about a dozen that total $57,725 for the whole administration building expansion project. “The estimated total project cost approved in the FY 2005/06 budget is $3,100,000 and the current estimated total project cost is $3,225,519,” the staff report said. Staff recommends approval of the change orders. Another item on the board’s agenda is a work authorization for the design services for the Honby Parallel Phase 2 project. A request for proposals was issued in late October for the work, and according to the staff report, three consulting firms were invited to propose and all firms responded. The firms that submitted proposals were Black & Veatch, Carollo Engineers and Kennedy/Jenks Consultants. The work would have a budget of $290,000. Copyright 2006, The Signal |
|||
|
|||
![]() |
Энергия | Информация | Вода | Сервисы |


